DOE, ERC orders NGCP to submit report on Luzon, Visayas supply disruptions


+
Add GMA on Google
Make this your preferred source to get more updates from this publisher on Google.

The Department of Energy (DOE) and the Energy Regulatory Commission (ERC) have ordered the
the National Grid Corporation of the Philippines (NGCP) to submit a comprehensive incident report
on the power supply disruptions in Luzon and the Visayas.

The two agencies tasked the NGCP to make a full accounting of the temporary power supply cut after its yellow and red alert declarations that affected the Luzon and the Visayas grids from May 12 to 14.

The DOE said the incidents placed millions of Filipino consumers at risk.

"The DOE is focused on ensuring stable power supply, protecting consumers, and enforcing
accountability across the power sector," DOE Secretary Sharon Garin said.

"The public deserves a full and transparent accounting of the incidents that led to these grid alerts, and we are requiring NGCP to comply fully with all reportorial and regulatory obligations," she added.

The NGCP's declaration of Red Alert status on the Luzon Grid on May 13 affected more than 200,000 customers in parts of Batangas, Bulacan, Cavite, Laguna, Metro Manila, and Rizal.

Garin said DOE technical teams have been actively and independently verifying the status of all affected generating units and transmission facilities, and assessing whether NGCP and concerned generation companies complied with dispatch instructions and restoration timelines during
the alert period.

The DOE said it expects the NGCP to submit the following vital information:

  • specific dates, time, duration, and areas affected by each alert declaration
  • the root cause or triggering factor of each supply deficiency or grid contingency
  • all generating units, transmission lines, and facilities that experienced forced outages,
  • deratings, or reduced availability
  • reserve and demand levels at the time of each alert
  • immediate corrective and load management measures undertaken; the restoration timeline and normalization actions
  • all related coordination with the DOE, ERC, and concerned generation companies


The DOE also emphasizes that under ERC Resolution No. 13, Series of 2010, NGCP is separately
obligated to submit an initial report within 60 minutes from the time of any system disruption.
Compliance with this reportorial requirement is being closely monitored by both the DOE and the
ERC.

"The DOE will continue to closely monitor grid conditions in both Luzon and Visayas, assess residual
supply risks, and coordinate with NGCP, the ERC, the Independent Electricity Market Operator of the
Philippines (IEMOP), distribution utilities, and all concerned generation companies to ensure the full
restoration of supply adequacy," Garin said. —LDF, GMA News